Witton Gilbert Sewage Treatment Works WINEP
As part of the Water Industry National Environmental Programme (WINEP), we will be installing new tertiary treatment plant to enable the site to contribute to a catchment wide reduction in phosphorous discharges. The improvement works will cost around £2.3m, and it’s one of 27 sites within the NWG region to receive an upgrade. Phosphorous is a nutrient and can cause algae to grow in watercourses, reducing biodiversity and river water quality.
Start Date: May 2024
Estimated End Date: April 2025
Partner: Galliford Try
Investment Value: £2.3 million
Status: Project Complete