Seahouses Wastewater Treatment Works Upgrade

We’re carrying out some essential repairs to the main distribution chamber at Seahouses Treatment Works. Over time, the concrete inside has worn down, with some cracks and areas where the steel underneath has become exposed. This is making the site harder to run and could lead to environmental issues if left untreated.

To keep everything running as normal while this work is carried out, we’ll install a temporary prefabricated chamber. Once that’s in place, we’ll carefully remove the damaged concrete using a high-pressure water technique and replace it with a new, durable lining.

We'll keep you updated through this community hub page, on the progress of the works.

Start Date: 20 July 2026

Estimated End Date: 4 December 2026

Partners: Mott MacDonald Bentley (MMB)

Investment Value: £2 million

Open for participation

Phases

Phases overview

Project Updates

16 June 2026 23:00 - No end date

Keep up to date with the latest news, progress and upcoming work on our project.

0 comments

No results found. Please try a different filter or search term.

Filters

Total posts: 0
There are no projects available.

Sorting changed to: New

No values available.

Selected zero tag filters.