Good morning everyone,
As activity across the site begins to reduce, you may notice fewer updates on the Community Hub. However, we'll continue to check in with you to keep you informed of our progress and share the latest project news.
Over the past week, we have continued removing stone and surplus material from the compound area and other working areas across the site. As a result, residents may have noticed an increase in wagon movements. These activities are expected to continue for the next couple of weeks.
Commissioning activities are progressing well and will continue over the coming weeks as we move closer to bringing the reservoir and pipeline into service. This marks an important milestone in the project and will help improve the resilience and reliability of the local water network.
We're also pleased to confirm that the fencing along Broom Court and around the reservoir has now been completed, with the exception of a small section adjacent to neighbouring land, which will be finished shortly.
Thank you for your continued patience and support. As always, don’t hesitate to add a comment if you if you have any questions.