Project Update from 30/10/2024
From "Felton Wastewater Treatment Works"
Go to the project
This month we've seen steady advancements on-site, The primary settlement tank has successfully passed water testing and is now being backfilled. This new tank will work along side the two existing tanks to remove larger solids and settle-able organic matter from sewage at the initial stage of the wastewater treatment. Additionally, pipework to the HST's (Humus Settlement Tanks) has been upsized to allow greater flow through the works. We've also dug trial holes to provide our design team with valuable data for further planning in order to upgrade the works. Our electrician's have also started on site to undertake a full electrical refurbishment of the works.
I want to extend my gratitude for your support and patience as we make improvements. If you have any questions or concerns, please feel free to leave a message below.