Project Update from 30/07/2024

From "Knitsley Sewage Treatment Works"

Go to the project

Civil works are progressing well on site, with the majority of the underground pipework complete and pumping stations almost complete. The next phase planned for the South of the site will be to get the mechanical and electrical installations underway. This should commence in August at the same time as the start of the software upgrades to both MCC’s (Motor control centres) on site.