Project Update from 29/01/2025
From "Eppleby Sewage Treatment Works Upgrade"
Go to the project
This is our first update of 2025 for the Eppleby Sewage Treatment Works, and I’m pleased to report that the team on Site have continued with the great progress, and I wanted to share this with you.
The electrical works are progressing as planned and the concrete surround and footpath prep around the Humus Settlement Tank (HST) are well underway.
The additional manhole for diverting flows to the HST has been installed and the distribution chamber weir is complete and 50% benched.
Moving onto the remaining duct chambers, I am pleased to advise that these are now complete.
Time critical works for the balance tank and floating arm installation were completed without issues on 20th January.
As always, if you have any questions regarding the works then please don’t hesitate to add a comment in the box below and a member of the Project Team will respond accordingly.
