Project Update from 29/01/2025
From "Teesside Transfer WINEP"
Go to the project
This week the team continue to test the new installed pipework as well as the Under Track Crossing (UTX) pipe which has been pressure tested and passed.
The valve slab is now installed including the steel fixing to the wet well.
Track monitoring is in place and will continue over the coming weeks.
Saturday 8 March 2025 the team will be working along the railway track to demobilise equipment from site. Noise and disruption will be kept to a minimum.
Please contact us direct if you have any questions at nwl.customer@esh.uk.com.