Project Update from 27/09/2024

From "Knitsley Sewage Treatment Works"

Go to the project

Progress on the civil works at Knitsley continues well and the pumping station at the south of the site is now complete. 

Due to the narrow access road, a rethink on the dosing kiosks has had to take place, with the result being we will now complete some additional works on site to enable smaller equipment to be delivered.

This will result in the overall works being prolonged for a two-three month period, with dosing now due to start around March 2025.