Project Update from 26/11/2024
From "Great Broughton Sewage Treatment Works"
Go to the project
We are now on Site and fully operational. The first few weeks have seen some great progress and hard work made by the Site Team, so I wanted to share this progress with you on today’s update.
- All of the reinforced concrete has been removed and the trench dug along the through Site to allow the ducting, wash water and PE rising mains which has been installed.
- Installed new 250di primary effluent pipe across the road ready to connect onto Material laydown area is complete along with topping off with tarmac plainings.
- 10no valves delivered from Affco
- Positive review of the level 1 plan with the Site Team.
As you can see, this is a fantastic start to the Project.
If you have any questions that you’d like to ask us, please don’t hesitate to add a comment in the box below and a member of the Project Team will respond accordingly.