I thought I’d add an update to share with you the great progress that has been made on Site recently, I have quite a lot to tell you!

Pumping station

The team have installed the 1050 ring and benched, and mass poured surround and built up the rings in for the pumping station to 3.75m.

6 rings in total have been installed and concreted in and all rings have now been surrounded with concrete along with 45M concrete used to surround the rings for the pumping station.

HST

The concrete surround has been poured up to 600mm below finished level and we have removed TW from the HST area.

We have barriered and added signage to create an exclusion zone.

Pipework from HST to pumping station inlet

The pipe work has been installed and backfilled using pipe bedding from HST to first manhole.

We have also installed the manhole and concreted this in and have connected the pipework either side of manhole.

Pipework excavation has been completed to allow works to carry on from manhole towards pumping station inlet.

DUCTS

We have installed ducts from the NPG to existing chamber near new SR pumping station.

As always, should you have any questions that you’d like to ask us, please add a comment in the box below and a member of the Project Team will respond as soon as possible.

Comments

Commenting is not possible because this project is currently not active.
Total likes: 1, total dislikes: 0
. You can no longer react to ideas in Eppleby Sewage Treatment Works Upgrade. You can no longer react to ideas in Eppleby Sewage Treatment Works Upgrade

Share

Posted by

Current status

Update