Project Update from 22/07/2024
From "Horsley Water Treatment Works Upgrade"
Go to the project
I am pleased to say that great progress continues to be made at Horsley with the commissioning of six new rapid gravity filters (see the image below), this is the 2nd stage of the water treatment process, where water is filtered through a layer of anthracite, sand and gravel. The rapid gravity filters (RGF) are expected to be fully operational within the coming weeks.
Works substantially completed this month have included the diversion of a gas main and the site wide reinstatement including footpaths.
We would like to thank you all for your continued support and patience while the works continue and that I hope we are not causing too much disruption in the village with the on going traffic. If you have any questions or queries please leave a comment below or contact us on the details provided and one of the team will get back to you.