Project Update from 20/02/2025

From "Warkworth Stanners SPS Refurb"

Go to the project

Since the return in January, we have been making good progress on site and we reached a key stage in the project this week. Our Supply partners, RetroFlo coordinated a crane lift on Tuesday 18th February to install a concrete cover slab for the pumping station, which was successfully completed. We will now continue with works inside the chamber and work our way up to ground level, completing the pipework and electrical connections.