I wanted to share some great progress with you, that the Team on Site have continued to deliver.
- The new MCC kiosk has been installed
- JHT attended to fit the steel grate flooring inside the MCC and they also installed the new balance tank.
- O’Connor Utilities came in to install the new mains cable for the site On Friday 13th December.
- Intelect attended to in pull in the cables
- The surround to the PS Tank and inlet manhole has now been concreted.
- We have built up most of the draw pits with brickwork and started installing the new lids.