Project Update from 17/01/2025
From "Durham Transfer WINEP"
Go to the project
As you might have noticed, we are now back on site, positioning and setting access covers to the shaft at Plawsworth Sewerage Treatment Works. The team are cleaning out and placing the gravel strip behind the MCC kiosk and generator.
Preparation for the concrete pour has begun at Plawsworth Sewerage Treatment Works. The team are using a 14-tonne excavator to reinstate the compound area and load away the hardstanding area before reinstating commences.
Access covers are being lifted into position and set into the shaft and the valve chamber ready for concrete.