Project Update from 10/09/2024
From "Horsley Water Treatment Works Upgrade"
Go to the project
Work on site is going well. We're almost done setting up the new filters, so temporary equipment can be removed soon. We've started working on the pre-dosing system, with only a few tasks left to complete. Preparation for the new chlorine contact tank has also started, which includes checking underground pipes, moving lights, and doing a trial to help finalize the design.
We would like to thank you for all your continued co-operation and patience while the works are ongoing, if you have any questions or issues please leave a comment below or use the contact details provided and one of the team will get back to you.
Comments
Please to comment.
Total likes: 1, total dislikes: 0
. Sign in to react.
Share
Posted by
Current status
Update