Project Update from 03/03/2025
From "Greatham Sewage Treatment Works"
Go to the project
The Storm Tank has now been constructed and the water test is scheduled for next week.
The access stairs and platform for the Storm Tank is in place, including the outlet pipework for the overflow has been installed.
Outlet pipework to take storm water back into the works via the recirculation pumping station is going in this week.
Commissioning of the sensor and telemetry equipment is scheduled for the Monday 10 March.
Extension of the palisade fence around the new part of the treatment works has been erected. The extension to the access road will be happening next week.
We will be looking to demobilise from site during the middle of March.