Project Update 6 October 2026
From "Pegswood Wastewater Treatment Works"
Go to the project
Good morning,
Since our last update, we have successfully completed the establishment of our main site compound, including the installation of our site cabins and the removal of the temporary set-up area.
As previously advised, arrangements have now been approved with the local authority to temporarily divert the Public Right of Way. The diversion will be in place from 9 October 2026 for a period of six months. Clear signage will be installed throughout the diversion route to help guide walkers safely, and a map has been provided to show the alternative path.
We have also completed a series of ground investigation works to support the development of the Sewer Overflow scheme. These activities included:
- Utility investigations to identify and avoid existing underground services.
- CCTV surveys of the existing sewer network.
- Borehole surveys to gather information on ground conditions.
- Reinstatement of all excavation areas following completion of the surveys.
We would like to thank everyone for their continued patience and understanding as we progress with these important investigations and preparations for the project.
If you have any questions or would like to share your thoughts, please leave a comment below. Alternatively, you can contact the project team at MMBCustomerServiceTeam@mottmac.com and someone will be happy to help.
Thanks,
The Project Team