Project update 5 November 2026
From "Sedgefield Flood Reduction"
Go to the project
An update on our NIDP works in your area.
Hi everyone
Since commencing the project, we have encountered some unforeseen challenges, including land access issues and network conditions that required additional investigation and changes to the design. As a result, phases 1 and 2 have taken longer than anticipated, impacting the overall programme and resulting in revised dates for the remaining phases.
The revised programme is outlined below:
Phase 1 - The Leas Cul-de-Sac
Works commenced on 21 September 2026 and remain ongoing. Activities within this area are now expected to continue until 12 March 2027, however this will be split over two periods from 21 September 2026 to 18 December 2026. Then 4 January to 12 March 2027.
Phase 2 - Main Section of The Leas
Works on the main section of The Leas (turning left from the cul-de-sac) are now programmed to take place between:04 January until 10 February 2026
Phase 3 - The Leas (Right of Cul-de-Sac)
Works in this area are now programmed to take place between:
11 February 2027 until 24 March 2024
Phase 4 - Cragside
Works within Cragside are now programmed to take place between:
Cragside from 25 March 2027 to 16 April 2027
Phase 5 - Cragside and The Meadows Junction
Works at the junction of Cragside and The Meadows, progressing northwards, are now programmed to take place between:
25 March 2027 until 15 June 2027.
Many thanks
The Project Team