Project update 4 November 2026

From "Cambois Environmental Improvements"

Go to the project

Hi everyone

We've now completed our survey work and are preparing to begin construction in the Cleaswell Hill area from 9 November 2026.

Working alongside our delivery partner Avove and subcontractors Ivor King and Sirius, we will be carrying out an initial phase of enabling works which is expected to last for approximately six weeks.

During this period, local residents may notice:

  • Increased construction vehicle movements in the area
  • Some noise associated with site activities
  • The establishment of a temporary site compound

The site compound will be located within the work area and will remain in place throughout the main construction phase.

Work will pause for the Christmas period between 23 December 2026 and 4 January 2027. Following the Christmas break, the main construction phase will begin and is expected to continue for approximately six months.

We'll continue to provide updates on the progress of the scheme through this Community Hub and will share further information about the main construction works closer to the time.

Thanks for your patience and understanding while we carry out these essential improvements.


Many thanks

The Project Team