Hi everyone,

Happy Friday! Please see an update of our progress below.

The new pump and kiosk have now been installed at the bottom of Westerton bank.

We are currently carrying out electrical connections and connecting to the Northumbrian Water system.

The pipework is nearly complete and we are still on target to turn on flows in December.

We thank you all for your cooperation during this time.

Should you have any questions please comment on this page or contacts us at NWL.Customer@esh.uk.com.

Alice Blackett

Customer Advisor