I wanted to update you on the progress made by the Site Team, it certainly has been a good month!

  • The new PST is now complete and has passed it's water test.
  • The new MCC and MCC kiosk have been installed.
  • NPG have completed a power upgrade to the works and the electrical install has commenced.
  • The new Inlet works gantry is now 100% complete.
  • We have just completed the connection onto the incoming rising main pipe to enable us to divert flows through the new works.

As the project Project progresses, we may take advantage of weekend working to continue with the great progress.

As always, if you’d like to ask us anything regarding the works, please don’t hesitate to add a comment in the box below and a member of the Project Team will respond accordingly.

Take care and speak soon!

Comments

Commenting is not possible because this project is currently not active.
Total likes: 1, total dislikes: 0
. You can no longer react to ideas in Aldbrough St John Sewage Treatment Works. You can no longer react to ideas in Aldbrough St John Sewage Treatment Works

Share

Posted by

Current status

Update