Hi everyone,

Works are progressing well at Westerton. We have located the pipes on the village green and carriageway and have built the flowmeter chamber for the booster station.

This week we have been carrying out temporary reinstatements in the village green following survey works. We will be going back into the village green in the future to connect the new pipework to the existing pipework.

In the next few weeks, we will be installing the pipework in the field up towards the village, ready to come into the carriage way which is estimated to start end of July 2025.

Should you have any questions please comment on this page or contacts us at NWL.Customer@esh.uk.com.

Thank you