Hello everyone, please see an update below on the progress of works throughout the Stanley area:
Park Road
Parmeter Street
Parmeter Street is currently closed as we lay the new surface water drain and connect the road gullies as we go.
Park Road
We have dug down and constructed a new manhole which will connect the existing combined sewer to the new sewer on Mundell Street. The excavation is backfilled and reinstated and all traffic management has now been removed.
Windemere Terrace
We have begun construction of the earth bund which will direct surface water to the swale that will be constructed at a later date. We have road cleaners on to ensure the roads are kept free from dirt.
Miners Green
The fencing has now been removed, and the grass has been cut.
School Lane
Drainage has now been installed, a new manhole constructed and the road temporarily reinstated. The road has now been reopened; however, we still need to conduct root cutting on the existing surface water drainpipe running up Fern Avenue, and then repair the footpath. #
Avon Road:
Tweed Terrace
We are currently working our way from Tweed Terrace West up to Wansbeck Avenue where a road closure is currently in place. We are also starting work along Tweed Terrace week commencing 2nd November where a rolling road closure will be in place.
Avon Road
Works were completed on Avon Road on Friday 23rd October, one week earlier than planned. All bus services are now running as normal.
Should you've any questions please comment on this page or contacts us at NWL.Customer@esh.uk.com.
Thanks
The Project Team