Project Update 29/04/2025
From "Great Ayton Sewage Treatment Works WINEP"
Go to the project
Hi all,
Let me give you an update on WINEP Great Ayton STW Storm Capacity:
The Interceptor Chamber Works are ongoing, we now moved on to the FRC (Formworks, Reinforcement, Concrete) stage. The base reinforcement in approaching completion, this will be followed by shuttering and concrete pour, which is planned for Thursday.
The dewatering solution has not progressed as hoped so we are currently looking into alternatives so that the shaft can proceed, we hope to have a definite way forward in the next few days.
In the background, the remaining design work is approaching completion, and all of the major procurement is progressing well.
Thanks for taking the time to read.
Dave Eden PM.