Project Update 28/07/2025
From "Coundon Burn Sewer"
Go to the project
Hi everyone,
Our Contractor, Active Tunnelling, have now excavated the drive pits at Manhole 01, Manhole 02 & Manhole 03. By close of play today they will have installed the first drain run between Manhole 01 & Manhole 02 also.
Esh Drainage Solutions have installed the over pumping pipework for phase 1 of the relining works. They will be testing the pipes and then commencing relining works this week.
Esh have been maintaining and extending the stone haul roads to allow safe access to working areas.
Please see photographs of our progress.