Hello everyone

We hope you are enjoying the start of Autumn. We would like to take this opportunity to give you an update of what’s been happening on site since our last update!

  • We have successfully completed the second section of underground drilling between MH02 and MH03
  • The first stage of connecting the new pipe to the existing sewer network is complete and the area has been reinstated
  • Drilling work has now started between MH03 and MH05, with the polit drilling complete
  • The construction of the new manhole at MH02 is progressing, with the base complete and work underway on the shaft
  • Temporary works at MH02 have been removed and the backfilling is nearly finished

Got a question?

Feel free to drop a comment in the comment box below, and a member of the Project Team will get back to you!

Many Thanks

The Project Team