Project Update 27/04/2026
From "Springwell Enhancements Project"
Go to the project
Hi all,
Please see below an update on site activities planned for this week:
- The final surface will be laid along both the Northern and Southern access roads, with both roads expected to be fully complete by the end of next week.
- Seeding works will continue in designated areas within the reservoir site.
- Works will continue at the Southern SuDS.
- Works to the Eastern SuDS are now complete, with fencing installation taking place this week.
We apologise for any inconvenience caused by the pothole repairs not being carried out last week. Sunderland Council will attend this week to complete the necessary repairs.
Please don’t hesitate to add a comment in the box below if you have any questions for the Team, we’d be happy to help.
Many thanks,
The Project Team
Comments
Please to comment.
Total likes: 1, total dislikes: 0
. Sign in to react.
Share
Posted by
Current status
Update
