Project Update 26/09/2025

From "Fenham Service Reservoir"

Go to the project

Hi everyone,

I wanted to share a quick update on the recent progress we've made as the Project continues to move forward.

The west cell has now been successfully brought back into service, which allows us to drain down the east cell in preparation for the next phase of works starting next week. As part of this phase, scaffold access will be installed to enable safety isolations to proceed. This will pave the way for the removal of the damaged penstock, which will be replaced with a new unit.

If you have any questions about the Project, please don’t hesitate to reach out — we’re always happy to help.

Speak soon,

Bethany