Project Update 26/08/2025
From "Westerton Reservoir Abandonment & Pumping Station"
Go to the project
Hello Everyone
Here are a couple of updates for you all.
Pumping station works are as follows:
The Inlet pipework from the hot tap connection has been installed pressure tested and back filled.
The flow meter chamber and bypass arrangement has been installed pressure tested and backfilled.
The Joiners and the Steel Fixers are currently installing the shutters and the reinforcing for the concrete slabs to be poured next week.
36m of pipe has now been installed, backfilled and tarmacked in the village. Traffic Management has been moved approximately 30m down into the village.
Should you have any questions please comment on this page or contacts us at NWL.Customer@esh.uk.com.
Much appreciated,
Alice Blackett