Skip to main content
Northumbrian Water Home

Project Update 25/04/2025

From "Teesside Transfer WINEP"

Go to the project

Hello all,

Important update on work in your area

The team have now commenced with topsoil reinstatements in various locations across the scheme, including Long Newton Lane, A67 and land close to the airport. Goosebeck to Mill Lane has begun and will be completed in the coming weeks.

Goose Beck STW

Both rising main connections are complete including the new 225 diameter drainage. All the groundwork and concrete edges are now finalised with the installation of the beams to the overflow chamber.

The new access road, which is in three sections has been excavated, stone added and concreted. Excavation and installation of the four concrete bases is achieved in readiness for the new posts. Electrical works continue, installing cabling, sensors and isolator in readiness for commissioning. 

Long Newton STW

The team have installed all the over pumping equipment, storage tanks and pumps which were made live to enable our proposed tank modifications.

Please contact us direct if you have any questions at nwl.customer@esh.uk.com

Thank you for your patience and support throughout these works.

Comments

Please to comment.
Total likes: 2, total dislikes: 0
. Sign in to react.

Share

Posted by

Current status

Update