Project Update 25/04/2025

From "Storm Overflows Environmental Improvements"

Go to the project

Hello all,

Important update on work in your area

Ludworth and West Rainton

We are pleased to advise that the construction work is now complete within Ludworth and West Rainton. The working areas have been reinstated although it may take a little time to fully establish, we appreciate your understanding while nature takes its course.

Stanghow Road, Lingdale

The road closure will be repositioned on Sandringham Road to the junction of Balmoral Road starting Monday 28 April, residents impacted by our work have been informed.

The attenuation tank has now been completed and topsoil reinstatement will begin over the coming weeks.

A priority system will also be in place from the roundabout on Balmoral Road to Whitwell Place, High Street, while the team complete further investigation and surveys.

Etherley Lane, Bishop Auckland

As mentioned previously work had been placed on hold due to urgent work in the area. Our team will return to site from Monday 28 April 2025. Traffic management will be in place on Etherley Lane using 2 way traffic lights.

Throughout the work our team may be required to work weekends as the work progresses. The site team typically work Monday to Friday, if it is necessary to work weekends the team will work between 8.00am and 16.30pm.

Please contact us direct if you have any questions at nwl.customer@esh.uk.com

Thank you for your patience and support throughout the construction stage of these works. 