Time for an update on WINEP Great Ayton STW Storm Capacity:
We have completed the work on the inlet pipework and manhole for the time being, though there will be a revisit to connect the manhole to the new shaft/storm tank and finalise the manhole.
We’ve now started the interceptor chamber which will eventually divert the flows from the existing storm overflow into the new shaft/storm tank. That’s excavated and shored, and the blinding has been poured, so we are just waiting for the reinforcement bar to arrive, and we can start on the structural work.
The shaft itself is on hold whilst we wait for the dewatering solution to reduce the ground water level, be we have managed to level the shaft out, so it is no longer listing.
The dewatering installation is complete and after a couple of false starts we now have a working solution in place which should be able to run continuously until the shaft is complete or at least in a position where the shaft construction no longer requires dewatering.