Project Update 24/02/2026

From "Hesleden Dene Pipe Bridge"

Go to the project

Hi everyone,

As we continue to progress through the early stages of the Project, here is an overview of the activities currently taking place:

Site cabins are now fully set up and operational following their installation over the past couple of weeks.

Stoning up works near the pipe bridge will continue as we prepare the area for the upcoming bridge demolition.

Construction of haul roads are ongoing to support the safe and efficient movement of vehicles across the site.

Access track development is progressing well, improving connectivity throughout the area.

Bridleway widening and strengthening has now been completed by the team.

As the Project continues, we will keep you updated as key milestones are reached.

If you have any questions regarding the Project, please add them in the comment box below and a member of the Team will be happy to respond.

Many thanks,

The Project Team