Project Update 23 July 2026
From "Springwell Enhancements Project"
Go to the project
Good morning everyone
I hope you're all well.
We wanted to update you on what you may see over the next couple of weeks:
Our main activity on site is the cleaning of the reservoir and pipeline. Alongside this, we will also be carrying out reinstatement, backfilling, and remedial works at the pipeline sites.
You may notice some material being removed via the entrance along Springwell Road.
Commissioning activities are due to commence shortly, and as a result, you may notice a slight increase in site traffic and personnel around the site entrance near Waterloo Road.
Thank you for your patience and understanding while these works are completed.
If you have any questions, please don’t hesitate to add a comment in the box below.
Thanks
The Project Team