Project Update 22 July 2026
From "South Stanley and Craghead Environmental Improvements"
Go to the project
Hello
I hope everyone is well and has been enjoying the lovely weather we have been having.
An update on our works around Stanley are as follows:
Avon Road:
The attenuation tank works are currently on hold whilst we wait for some Ground Investigation results returning. We have commenced the drainage run on the west side of Marx Crescent where a road closure will be in place from Monday 27th July 2026 for up to 3 weeks.
We're continuing works from the rear of Avon Road up Tweed Terrace where we are currently working on the 4-way junction to install a new manhole. We will continue to work our way North as works progress. Reinstatement works are being carried out this week on the road to the rear of Avon Road and Tweed Terrace which will see the road being reopened.
Park Road:
The combined sewer installation is progressing along Charlotte Street with works due to commence on Parmeter street week commencing 27 August 2026 where a road closure will be in place for approximately 4 weeks.
The final manhole has been constructed on the verge on Hustledown road where we have been working on the Surface Water Sewer. Reinstatement works are to commence and all fencing to be removed.
We're progressing well on Rydal Avenue, and expected to be complete in early August.
The basins on the green space on Greenlands is now complete and fencing will stay in place until the grass is established.
Should you've any questions please comment on this page or contacts us at NWL.Customer@esh.uk.com. Please see our images below to view our works taking place.
Thank you
The Project Team