Please see below current progress of works taking place at Coundon Burn.

ESH gang have removed a section of the temporary stone access track between Manhole 1 and Manhole 2. Later reinstated Ancient Woodland area including replacing Ancient Woodland topsoil under supervision of Ecology Clerk of Works.

The Gang have completed Open cut drainage works between Manhole 6 and Hydrobrake Chamber. 

Drainage works at the West side of the Attenuation Tank are in progress.

We are continuing to backfill around the North & South side of the Attenuation Tank using selected excavated materials.

The gang are preparing the ground for drainage works to the East side of the Attenuation Tank towards Manhole 10.

Should you have any questions please comment on this page or contacts us at NWL.Customer@esh.uk.com.

Thanks,

Alice Blackett