Killingworth - Project Update 19 October 2026
From "Ouseburn Wastewater Improvements"
Go to the project
Hi everyone
Works at Killingworth Lake are progressing well, with several key activities now completed across the site. The mass concrete infill and the lifting of the existing weir plate have been completed.
The removal of the 550mm–150mm land strip has been carried out, in preparation of seeding. Works are ongoing to remove the existing trash screen and fill the voids below and above the walls. The new trash screen and runners will be delivered to site, ready for installation.
We are aiming to complete the remaining works by the end of this week, subject to the seeding and delivery. We will continue to monitor progress and provide further updates as the works progress
Thanks
The Project Team

