Project Update 19 October 2026
From "Hury Reservoir"
Go to the project
Hello everyone
Over the last few weeks, the team have been working on all four pipe support foundations which have been successfully shuttered, poured and backfilled, allowing approximately 110 revetment stones to be replaced within the wet-side working area. The area was completed four days ahead of schedule, enabling the reservoir level to be increased by 5m.
A temporary wave wall has been installed using legato blocks where the existing wall was removed for the 2027 works. This has allowed water levels to be raised back to current supply levels.
Works have now commenced on the dry side, with coring holes being drilled into the existing spillway wall. Installation of the cofferdam for the outfall structure is expected to begin imminently.
Thanks
The Project Team
