We continue to install pipework on the grass verge on Hustledown Road. We are temporarily tarmacking the footpaths as we go, so that we can reopen for residents.
We are progressing on Pine Street installing the surface water drainage and are extending the road closure further up pine street to the junction towards John Street.
We are still progressing on the Foul Water drainage on Keswick Road. The Tarmac is being reinstated on Rydal Avenue so that we can get that section reopened.