Skip to main content
Northumbrian Water Home

Project Update 19/11/2025

From "South Stanley and Craghead Environmental Improvements"

Go to the project

Hi everyone,

We continue to install pipework on the grass verge on Hustledown Road. We are temporarily tarmacking the footpaths as we go, so that we can reopen for residents.

We are progressing on Pine Street installing the surface water drainage and are extending the road closure further up pine street to the junction towards John Street.

We are still progressing on the Foul Water drainage on Keswick Road. The Tarmac is being reinstated on Rydal Avenue so that we can get that section reopened.

Should you have any questions please comment on this page or contacts us at NWL.Customer@esh.uk.com.

Alice Blackett

Customer Advisor

Esh Stantec

Comments

Please to comment.
Total likes: 2, total dislikes: 0
. Sign in to react.

Share

Posted by

Current status

Update