Project Update 19/11/2025

From "Westerton Reservoir Abandonment & Pumping Station"

Go to the project

Hi everyone,

A small update for you all on the works at Westerton Village.

We are currently testing and flushing the new system to ensure the water quality is good enough to connect to the network.

All pipes are completed, flushed and tested.

We are waiting for test results back prior to final connections to the mains.

The pumps are being tested this week for flows, pressure and alarms.