Good afternoon,

The team are beginning to install new curbs within the Sewerage Treatment Works (STW) prior to tarmac starting week commencing 23 June 2025. The motor control centre (MCC) will be installed in July, this will be the centralised system to control and manage the equipment within the STW.

Pathways are being erected and concreted ready for our contractor Retroflow to begin maintenance work. Once all work is complete the team will begin reinstatements, within the area.

Should you have any questions please comment on this page or contacts us at NWL.Customer@esh.uk.com.

Thank you for your patience and support throughout the construction stage of these works. 