Project Update 19/06/2025
From "Teesside Transfer WINEP"
Go to the project
Hello all,
Important update on work in your area
The team have commenced and completed the removal of Oak Tree compound and access haul road, including the topsoil reinstatements along with the removal of our temporary site entrance off Yarm Road.
Following previous topsoiling operations, we have continued with cultivating and seeding which are now partially complete with the remainder due to be carried out over the next couple of weeks.
New pumps have been installed and flows turned to Goosebeck, with final commissioning carried out by our contractor Retroflo.
Please contact us direct if you have any questions at nwl.customer@esh.uk.com
Thank you for your patience and support throughout these works.