With the bank holiday fast approaching, this update outlines the planned activities on site for both this week and the week commencing 25 May.
W/C 18 May
- Seeding activities will be carried out around the reservoir.
- The new site compound set up
- Wagons will continue to access the compound area to remove stone and other materials.
W/C 25 May
- Installation of the boundary fence and the post and rail fence.
- Installation of the remaining sections of the security fence, followed by installation of the site gates the week after.
- Much of the visible activity over the next couple of weeks will take place within the compound area.
If you have any questions, please don’t hesitate to leave a comment in the box below and a member of the Project Team will respond accordingly.
Many thanks,
The Project Team
Comments
Please to comment.
Total likes: 1, total dislikes: 0
. Sign in to react.
Share
Posted by
Current status
Update