Project Update 17/02/2026
From "Hesleden Dene Pipe Bridge"
Go to the project
Hi everyone,
I hope you’re having a great week so far.
We would like to share an update on the works taking place on Site this week as we continue progressing through the early stages of the project.
The Site Cabins have now been installed and will become fully operational over the next week.
This week, the team will be completing the strengthening works to the bridleway, helping to ensure safe access for both the public and site traffic.
In addition, the Site Team will begin importing stone to create a road up to the pipe bridge and establish a working platform. This platform will support the safe demolition of the pipe bridge when we reach that stage. The enabling works required for the demolition are expected to take approximately two weeks. We will provide a further update once we are ready to move into the demolition phase.
Stone will also be placed in areas within the surrounding fields as part of the ongoing preparation works.
Please keep an eye on the Hub for continued updates as the project progresses. If you have any questions, feel free to add a comment below, we’re happy to help.
Many thanks,
The Project Team