Hi everyone,
Over the past month, we’ve made steady progress with the installation of the secondary steelwork including the coarse bar screen to deflect big debris at the front of the new structure, which is now underway as planned and on schedule.
Once the secondary metalwork is complete, we’ll move on to installing the mechanical and electrical elements needed for the new screens. This stage will begin in early autumn, keeping us on track for the new screens to be installed in early 2026.
We truly appreciate your patience and continued support while our work is ongoing.
If you have any questions or concerns about the project, please don’t hesitate to get in touch with us using the contact details provided
Thank you