Skip to main content
Northumbrian Water Home

Project Update 16/09/2025

From "Horsley Water Treatment Works Upgrade"

Go to the project

Hello everyone, here is this months update on our work at Horsley, The excavation of the cofferdam is progressing well, and we are on track to complete this element of works required to enable the build of the new Chlorine Contact Tank by early October. Once the excavation is completed, we will be able to start the temporary reinforced concrete propping slab.  

Work on BHPS pipework replacement is also progressing as planned, no all the old pipework is removed we have commenced installation of the new pipework.

If you have any questions you’d like to ask us regarding the work, please don’t hesitate to reach out by adding a comment in the box below. 

Comments

Please to comment.
Total likes: 1, total dislikes: 0
. Sign in to react.

Share

Posted by

Current status

Update