Project Update 16/03/2026
From "Springwell Enhancements Project"
Go to the project
Hi everyone,
The landscaping contractor has began with planting along the Northern Boundary of the Reservoir. They will also be returning to replant hedges and reinstate fencing along Springwell Road from Monday 16th March, where these were temporarily removed to allow access.
As progress on site continues, work on constructing the Southern Access Road will carry on this week. To allow the team to work safely in this area and complete the construction of the road, traffic management will be in place along Mount Lane.
We have included a drawing showing the location of the temporary traffic lights, which will remain in place until Friday 27th March.
Over the next few weeks, you may also notice the gradual reduction of the site compound. Some of the site cabins and stone will be removed as part of this phase of work.
Thank you for your cooperation while traffic management was set up along Mount Park Road to support the relocation of the topsoil bund into the reservoir site. This part of the project is progressing well, and we kindly ask road users to be mindful of local speed limits to help maintain a safe environment for everyone.
A quick reminder that some members of the Project Team will be attending the Springwell Village Residents Association meeting tomorrow at Springwell Social Club at 6:30pm.
If you have any questions about the project, please feel free to add them in the comment box below.
Many thanks,
The Project Team