Project Update 16/01/2026
From "South Stanley and Craghead Environmental Improvements"
Go to the project
Hi everyone and Happy New Year to you all.
Please see below an update on our works in South Moor:
We are currently working on Hustledown road at the bus stop to upsize the existing sewer and tie out newly installed sewer into the network. Traffic lights will be in place until 30th January 2026.
We continue the installation of the combined sewer on Keswick Street working towards the top of Windermere Terrace.
The works on Pine Street heading towards John Street continue as we install connections for the surface water separation.
We will be carrying out some excavation works within the grassed area, south of Rydal Avenue to locate and terminate redundant electric cables.
Should you have any questions please comment on this page or contact us at NWL.Customer@esh.uk.com.
Thank you
Alice Blackett
Customer Advisor