Hi everyone, update as follows:

The ESH Stantec Gang have continued the bulk excavation works in preparation for installation of precast concrete Attenuation Tank.

In addition to this, the gang have also been following behind Active Tunnelling, constructing manhole chambers for the new pipework.

Active Tunnelling have completed auger bore pipework between MH05 and MH06.

Esh Drainage Solutions have continued relining works through to Phase 2. Lining is currently taking place through the Railway Embankment culvert.

Ken Rodney Construction is currently welding up directional drill pipework, South side of Coundon Burn Watercourse.

Should you have any questions please comment on this page or contacts us at NWL.Customer@esh.uk.com.

Thanks,

Alice Blackett