Project Update 14/05/2025

From "Cullercoats Bathing Water Borehole Drilling"

Go to the project

Hi all,

We are experiencing some delays due to unforeseen ground conditions & rock formation, which has meant each location is taken more time than we initially anticipated. Currently our expectations are that all work will be completed by the 6th of June 2025, however, again this will depend on operational changes.

We sincerely apologies for an disruption or inconvenience that the ongoing work may be causing you.

Please see below an updated timescales and dates for each location:

  • YS4 - Now completed
  • YS1 – Commencing on the 21st of May 2025
  • YS 7 – Work now completed, currently demobilising from site
  • YS 8 – Work currently in progress
  • YS6 – Work currently in progress
  • CM1 - Work now completed, currently demobilising from site
  • YS5 – Commencing on the 14th of May 2025 